Peoject Status Tracking - Free Download
4.3, 3950 votes
Please vote for this template if it helps you.
Peoject Status Tracking
Peoject Status Tracking
1
12/6/2007 Project Scheduling and Tracking 2
Agenda
Project Scheduling
– work breakdown and task definition
– task dependency (PERT) analysis
– milestones and Earned Value Analysis
– resource and staffing dependencies
– time lines (Gantt Charts)
– staffing levels (PNR curves)
Project Status Tracking
– Using EVA to measure progress
Automated Scheduling tools
12/6/2007 Project Scheduling and Tracking 3
Project Scheduling
decompose project into
distinct tasks and subtasks
establish dependency
relationships among sub-tasks
estimate the size of, and work to
accomplish each sub-task
identify or define
project milestones
characterize the required
resources for each sub-task
identify available resources
assign dates to initial tasks
assign resources to tasks
acceptable
yes
12/6/2007 Project Scheduling and Tracking 4
Work Breakdown
hierarchical decomposition of work
– independent sub-tasks that sum to the whole
– can be based on either tasks or goals
– both process- and problem-centric
sub-tasks are fundamental unit of work
– the granularity of work estimation
– the granularity of assignment & scheduling
– the granularity of task inter-dependencies
– the basis for progress tracking
granularity will evolve with the project
A
1
A
2
A
3
12/6/2007 Project Scheduling and Tracking 5
Task Dependencies
input/output relationships between tasks
may be strict
e.g. system test starts after component integration
– may allow overlap
e.g. design can start one month after architecture
process-mandated pre-requisites
– support training must precede beta shipment
these dictate the order of scheduling
– they also determine the (longest) critical path
B
1
12/6/2007 Project Scheduling and Tracking 6
Dependencies (PERT charts)
decompose project into
distinct tasks and subtasks
establish dependency
relationships among sub-tasks
identify or define
project milestones
estimate the size of, and work to
accomplish each sub-task
characterize the required
resources for each sub-task
identify available resources
assign dates to initial tasks
assign resources to tasks
B
2
B
3
12/6/2007 Project Scheduling and Tracking 7
Establish Project Milestones
Specific and Measurable
– an objectively ascertainable moment
– avoid subjective assessments
Relevant measures of project progress
– goals achieved, work completed
– not merely hours of work done
Timely (relatively closely spaced)
– enable fine-grained progress tracking
– accurate assessment of work state and rate
C
1
C
2
C
3
Peoject Status Tracking Previous Page Peoject Status Tracking Next Page
source: cs.pomona.edu
Peoject Status Tracking
Previous

1/4

Next